The first stage pouring work of gas turbine foundation of Bahrain Alba Power Station 5, Block 4 CCGT is completed smoothly.


*

At 5:30 of November 22, 2022, the first phase of pouring for the gas turbine foundation of Bahrain Alba Power Station 5, Block 4 CCGT was successfully completed, marking the successful realization of another milestone of the project.

The pouring work started at 20:40 of November 21, 2022. All the members of the project had worked hard and put two pump trucks into the construction at the same time, and it lasted 9 hours. Finally, the first stage of pouring work of gas turbine foundation was successfully completed and 1070 cubic meters of concrete were poured.

The project attached great importance to this pouring work. Before the pouring work began, all professional departments organized special meetings, formulated perfect pouring construction plans, and sorted out the pouring punchlist, checked and improved it every day. Before pouring, the project carried out detailed safety and technical disclosure. During the pouring process, the owner, supervision and professional personnel kept a close eye on the site to ensure the orderly progress of the pouring work.

At present, the construction tasks of the project site are being pushed forward in an orderly manner. In the next step, the project will continue to carry forward the work style of "initiative, accountabilities, persistence", and promote the follow-up construction tasks of the project with high quality and high efficiency.