Myanmar Thaketa O&M Gas Fired Project completed the 2020 power generation task 44 days in advance


*

Up to 03:00 on November 17, 2020, Myanmar Thaketa O&M Gas Fired Project has completed 728053.34 MWh of on-grid power generation, reaching the 2020 power generation target 44 days ahead of schedule.

At 10:18 am, the project held a celebration ceremony in the CCR. Zhao Jin, chairman of the United Energy Corporation, which is the owner of the project, paid a special visit to the celebration on site to express his sincere congratulations to the O&M team.